The long-awaited footbridge connecting Metro and Rapid Rail Link in Ghaziabad remains stalled as 2025 progresses. Will the crucial infrastructure finally be completed this year, streamlining commuter travel?
Source Image: news18
Metro–Rapid Rail Link: Footbridge Project Stagnates
Two years after work began, the footbridge intended to link Ghaziabad’s Metro station with the Rapid Rail Link is still incomplete. Originally scheduled for inauguration in late 2023, the project has been delayed repeatedly. Locals report that structural pillars and steel frames remain idle, and debris is clogging pedestrian pathways — a daily inconvenience and safety hazard.
Reasons Behind the Delay
Several factors have contributed to the footbridge’s standstill:
-
Bureaucratic clearances: Land acquisition around the Metro station has hit legal snags.
-
Contractor changes: Midway replacement of contractors resulted in work disruptions.
-
Supply chain issues: Delays in material delivery, especially steel beams, have hampered progress amid rising prices.
The Commuter Predicament
Commuters are bearing the brunt. Without a safe footbridge, thousands daily are forced to cross busy roads or take long detours, exposing them to traffic risks—especially during peak hours.
Local Government’s Commitments
City officials now pledge completion by December 2025. The municipal body has released an updated timeline:
-
July–September 2025: Resume steel installation
-
October–November 2025: Complete walkway decking and roofing
-
December 2025: Final inspections, lighting, and accessibility features
However, skeptics argue that without tight oversight, these deadlines may slip again.
Looking Ahead: What Needs to Happen
To ensure the footbridge opens this year, the following steps are critical:
-
Expedited land and environmental clearances
-
Transparent contractor management with penalties for slippage
-
Community engagement to monitor daily progress
-
Scheduled audits to keep material procurement and labor on track